Road closures directly affecting Walberswick
As everyone will already be very aware, there are currently a large number of changes being made to our local roads due to the construction of Sizewell C (SZC) and the following will be particularly impactful on Walberswick over the next few months:
1) Following the completion in the summer of the first part of the B1387 improvement between the water tower and the A12, the work at the B1387/A12 junction work has now been scheduled for 23 November to 8 December. This will entail the B1387 between the water tower and the A12 being closed at night from 8pm to 5am during this entire period. Traffic lights will be in use on the A12 at this junction during this time. When the junction work is completed, the road will be reopened.


2) Once the B1387 is reopened, SZC then plans to close the B1125 through Blythburgh. That means that everyone exiting Walberswick will need to use the B1387 whether going north or south. The work in December will be temporary and will then be replaced with a permanent closure design to be finished by March 2027. This is to ensure that Sizewell workers will use the A12 and not the B1125. Given plans for some 10,000 workers going to the SZC site, trying to keep these thousands of vehicles off the B1125 will be critical.

3) At the same time that the work is ongoing around the B1387, traffic calming measures will be undertaken in Westleton village on the B1125. The road is expected to remain open into the village albeit there may be traffic lights. This work should be completed by Christmas.
4) Essex Water is also undertaking work at the B1125 at the southern end of Westleton village and have closed the B1125 south of Westleton for 4 months until March 2027.
SZC are planning on sending out the above information via mail to all residents in the coming days
Walberswick Parish Council